Welcome to the AFK Mods bug tracker. In order to report an issue, you need to have a VALIDATED account to post one. Once you have followed the link the registration email sent you, please select a project from the drop down menu below. Select “Open New Issue” and fill out the form with as many details as possible.

Issue Data
Status: Needs User Feedback
Issue Type: Bug Report
Project: Unofficial Skyrim Special Edition Patch
Component: Skyrim SE: Hearthfire
Category: Locations
Assigned To: Nobody
Platform: All
Severity: Low
Votes: 0
Watching: N/A
Opened By DayDreamer on Jun 13, 2022 7:28 am
Last Edited By Arthmoor on Jun 17, 2022 10:53 pm

Issue #32448: Alchemy tower recipe has wrong number of doors

 
There should be 2, not 3.

Found two related forms:

BYOHHouseRecipe150Room8ADoor [COBJ:03003CAB]
BYOHHouseRecipe350Room8BDoor [COBJ:0300957C]

Are there others that need to be fixed?



Attached Files:

byohRoom8Alchemy.7z

Comments

2 comment(s)
Arthmoor said:
 
I'm not sure what you have proposed as a fix is accurate either.

I started up a game using LAL to accelerate the building of the main house. Then went to the drafting table outside to add the Alchemy Laboratory. Once that was set up, I went to the workbench and asked it to build the doors. After feeding it the supplies it wanted I went back behind the house to note that 2 doors were placed. These are double doors, not single doors. So given how the formulas work, I don't think 6 hinges and 6 nails are actually enough. It should be 8 hinges, and in theory 16 nails to put those hinges into place.

Then assuming that each log represents one half of a double door, it should likely have been 4 logs instead of 3 to put these in. No idea where the iron fittings are supposed to enter into this, but chances are that too should be 4, not 3.

But - it should be 2 locks because only one side of each pair of double doors would need a lock.

I'm also not sure why you have 2 COBJ records listed. The way this system works you should only be dealing with one at a time.

subhuman said:
 
I'm not presenting this as a strong opinion on the matter either way, just as another factor for consideration:

But - it should be 2 locks because only one side of each pair of double doors would need a lock.

...unless it's intended that you're pre-building the materials for the external trapdoor to the roof.
The trapdoor doesn't appear until you've built later sections of the tower, but it is a door, would need hinges, and a lock on it would make sense as well since it opens to the outside.
I don't believe you get charged for those materials when adding the canopy, but they (logically) had to come from somewhere.

Showing Comments 1 - 2 of 2